Accountability Dashboard September - December 2021

Accountability Dashboard September - December 2021

Listening, learning, and reporting back to our community. 

 

Accountability Dashboard  September - December 2021 

The IBR Accountability Dashboard is a transparency tool designed to share engagement metrics and hold the program accountable to the public. Ongoing and inclusive community engagement is critical to identify a solution that balances differing regional perspectives and best serves the complex needs of the variety of users. The metrics below are the results of community engagement efforts conducted from September - December 2021. Additional engagement opportunities will continue throughout the life of the program.

Read the 2021 Fall Community Engagement Report

Listening

Meetings Held

31

September - December 2021

Website Visitors

16,335

September – December 2021

Social Engagements

30,000+

September – December 2021

Advisory Committee Meeting Engagement

September – December 2021

Listening Session Participants

307

September – December 2021

Outreach to Organizations

300+

September – December 2021

Community Working Groups

4

September – December 2021

Community Outreach Partners

11

September – December 2021

Newsletter Subscribers

6,756

Subscribers year-to-date

Accessibility

September – December 2021

Listening Session Participants

September – December 2021

Comments Received

1,853

September - December 2021

Media Stories

42

September - December 2021

Learning

Design Options

The program is seeking feedback from its Community Advisory Group, Equity Advisory Group and Executive Steering Group, in addition to the eight partner agencies, with the goal of receiving approval in July 2022. An update on progress, including the detail of the Modified LPA, is due from the Washington members of the bi-state legislative committee to the Washington State Legislature by August 1, 2022. The goal is to identify a Modified LPA by summer 2022 to submit for environmental review. During the environmental review phase, the IBR team will continue to advance a preliminary design, acquire permits and update the cost and funding analysis. Construction is estimated to begin in late 2025.

<p>Hayden Island / Marine Drive Full Interchange view from North Portland with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from North Portland with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from Hayden Island with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from Hayden Island with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from Marine Drive to Hayden Island with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from Marine Drive to Hayden Island with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from Hayden Island with two bridge option.</p>
<p>Hayden Island / Marine Drive Full Interchange view from Hayden Island with two bridge option.</p>
<p>Downtown Vancouver Two Bridge Option shows High Capacity Transit hugging 1-5 and a Washington St option. </p>
<p>Downtown Vancouver Two Bridge Option shows High Capacity Transit hugging 1-5 and a Washington St option in addition to a shared use path ramp. </p>
<p>Downtown Vancouver Two Bridge Option shows High Capacity Transit hugging 1-5 and a Washington St option in addition to a shared use path ramp. </p>
<p>Downtown Vancouver One Bridge Option shows High Capacity Transit hugging 1-5 and a Washington St option in addition to the shared use path. </p>
<p>Downtown Vancouver One Bridge Option shows High Capacity Transit hugging 1-5 and a Washington St option.</p>
<p>Downtown Vancouver One Bridge Option shows High Capacity Transit hugging 1-5 and a shared use path to Downtown Vancouver.</p>

Equity Advisory Group Highlights

  1. Reviewed and discussed high-capacity transit investment options, technical, and equity measures developed to better understand how the options perform relative to each other, and initial findings of technical and equity analysis.
  2. Began development of an accountability tool that will be used to demonstrate how the Equity Framework is being implemented throughout the program.
  3. Discussed how the program can ensure high-capacity transit investments contribute to equity objectives. Recommendations include incorporation of universal design principles, ensuring transit mode selected does not further displace or cause harm to equity-priority communities, hire locally and within low-income communities, ensure job training opportunities are in place before construction begins, and work with program partners to incorporate equity objectives into ongoing operations after bridge construction ends.

Community Advisory Group Highlights

  1. Discussed the process for reaching a Draft Modified Locally Preferred Alternative (LPA) and how the group will provide feedback on key components.
  2. Looked at for high-capacity transit investments and emphasized the need to focus on equity, travel efficiency and reliability, and a data-informed process.
  3. Evaluated Hayden Island/Marine Drive design options and shared their desire to hear from the freight community, view more data related to travel times, congestion, and cost, and learn more about how an interchange footprint will impact the Hayden Island community.
  4. Reviewed their role in the approval process of the Draft Modified LPA, voted on their top values to use as evaluation criteria in considering design components, and ranked which design components to prioritize for review and consideration. Transit options ranked highest, followed by number of auxiliary lanes.
  5. Reviewed and discussed transit investment options, technical and equity measures developed to better understand how the options perform relative to each other, and initial findings of technical and equity analysis.

Bridge Stories

What’s your story?

We want to hear your experience using the bridge, what the bridge means to you and the benefits a replacement bridge could provide.

Send your story to info@interstatebridge.org. |  View more bridge stories.

What we've heard and how we're responding

We've heard the community values low-barrier engagement options and the opportunity to have meaningful conversations with the program. 

We've heard community members are interested in learning more about the program's design process and sharing their feedback.

We’ve heard social media is one of the preferred ways our community would like to be engaged.


Reporting

The program will continue to share accountability reports and develop additional reporting metrics. The most recent accountability reports include the 2021 Program Progress Report and 2021 Community Engagement Reports. The 2020 Conceptual Finance Plan provides an early and high-level overview of initial estimated funding and financing needs and potential sources.

Current reports are listed to the right. For more information, visit our library. 

Program Timeline

 

Disadvantaged Business Participation Goals

Through January 2022*

Current Funding Sources

* An additional $1 billion is dedicated through the Move Ahead WA transportation package for future work to complete construction.

Current Expenditures

Expenditures Through December 2021*

GEC Expenditures Through December 2021 by Category

Expenditures Through December 2021*

Consultant Representation by Geographic Area

Through January 2022*