Documents + Information
A compilation of program related documents and materials are provided for reference.
Financial Reports
Below, find updated finance reports documenting information about the economic impact analysis, tolling analysis, financial planning, and risk assessment efforts completed for components included in the Modified Locally Preferred Alternative which were approved for further analysis in July 2022. Cost estimates and financial plans will continue to be updated as the program is refined.
For more information about cost estimates and finance plans, please see the Cost, Funding & Economic Benefits page.
- Toll Traffic & Revenue Study Fact Sheet (Nov.2023)
- Level 2 Traffic and Revenue Study (Nov.2023)
- FTA Request and Response for Capital Investment Grant (Revised Sept.2023)
- Economic Impact of IBR Program Capital Investment (Apr. 2023)
- IBR Financial Plan (Apr. 2023)
- Quantitative Risk Assessment Summary (Apr. 2023)
- Quantitative Risk Assessment Report (Apr. 2023)
Technical Documents
Understanding River Navigation Considerations
River Crossing Options Executive Summary
Movable Span Options Executive Summary
River Crossing Option Comparison
River Crossing Bridge Clearance Assessment Report – Movable Span Options
Immersed Tube Tunnel (ITT) Analysis
- ITT Concept Assessment Document (Rev2. September. 2023)
- Context for the ITT Analysis
- Conceptual Assessment Presentation
IBR Recommended Modified LPA
The Modified Locally Preferred Alternative (LPA) is a foundation for what to study in the Supplemental Environmental Impact Statement. The program acknowledges that additional work and analyses beyond what is reflected in the Modified LPA will be necessary as the program moves forward. Information about the Modified LPA can be found in the documents listed below.
- Program Area Map*
- Program Area Active Transportation Improvements Map*
- IBR Recommended Modified LPA- Factsheet
- IBR Recommendation for Modified LPA - Summary Memo
- IBR Recommendation for Modified LPA - Briefing Packet
- IBR Recommendation - Summary Graphic
- Program Milestones
The Modified LPA was endorsed by all eight local partner agencies in summer 2022. As part of the endorsement process, the program received 175 conditions reflecting partner priorities and requests for additional work. The majority of agency conditions were in alignment with others received and many were already included in program plans for upcoming work. The initial responses sent to each agency identifying how these conditions are being incorporated into current program plans are linked below. Conversations have been ongoing with partner agencies to better understand their requests and identify how the remaining conditions that require more consideration will be addressed.
- Modified LPA Partner Conditions (Dec 2022)
Responses to Conditions (2022)
Responses to Conditions (2024)
Previous Documentation
*Remediation available upon request.
Bi-State and Legislative Reports
- Bi-State Agreement Options Assessment (November 2021, remediation available upon request)
- 2022 Interstate Bridge Replacement Progress Report (December 2022)
- 2022 Interstate Bridge Replacement Progress Report (June 2022)
- 2021 Interstate Bridge Replacement Progress Report (December 2021)
- Bi-State Legislative support for the Interstate Bridge Replacement program (July 2021)
- Program update on funding questions to Oregon Transportation Commission (January 2021)
- Legislative Information Factsheet (December 2020)
- Interstate Bridge Replacement Progress Report (December 2020)
- Conceptual Finance Plan (December 2020)
- Interstate Bridge Replacement Progress Report (December 2019)
- Memorandum of Intent on Replacing the I-5 Bridge over the Columbia River (November 2019)
Environmental Documents
- Re-Evaluation of the Columbia River Crossing Final Environmental Impact Statement and Record of Decision (ADA Compliant) (February 2022)
- Re-Evaluation of the Columbia River Crossing Final Environmental Impact Statement and Record of Decision (original) (February 2022)
- Cover Letter and Federal Agency Response (May 2021)
- Columbia River Crossing: Environmental Process and Permitting
Memos on solutions that do not meet the Purpose and Need
- Cover Letter
- Common Sense Alternative II
- High-Speed Rail
- Third and Supplemental Bridge options
- Tunnel River Crossing
Permitting
Community Engagement
Community Survey Data
Community Engagement Report (September-December 2021)
2021 Year in Review By the Numbers
Community Engagement Archives
Community Engagement Report (September-December 2021)
Community Engagement Report (February-March 2021)
Elevating the Voices of Equity
Community Conversation Preliminary Results
Open House Feb 16-Mar 1 2021
Open House Boards
Fact Sheet
Community Engagement
- Kết nối cộng đồng
- Вовлеченность сообщества
- Залучення громади
- 社區參與
- Ka Qeybgalka Bulshada
- 지역 사회 참여
- Participación de la comunidad
Community Events
- Sự kiện cộng đồng
- События сообщества
- Події громади
- 社区活动
- 社區活動
- Dhacdooyinka Bulshada
- 커뮤니티 이벤트
- Eventos comunitarios