Program News

OR and WA move closer to U.S. Coast Guard bridge permit

Published: Tuesday, November 18, 2025

Program Contact: Kimberly Webb, Interstate Bridge Replacement Program, 1-844-427-6397 (844-IBR-NEWS)  | media@interstatebridge.org

Oregon, Washington move closer to U.S. Coast Guard bridge permit for I-5 Columbia River replacement bridge

Agreements with river users support the IBR Program’s pursuit of previously permitted fixed bridge height.

Vancouver, WA – Oregon and Washington moved one step closer to replacing the aging Interstate Bridge after signing agreements with the four river users identified as being affected by a proposed fixed-span bridge across the Columbia River.

These agreements paved the way for the Oregon Department of Transportation (ODOT) and Washington State Department of Transportation (WSDOT) to submit an updated Navigation Impact Report on behalf of the Interstate Bridge Replacement (IBR) Program to the U.S. Coast Guard proposing a fixed-span bridge of 116 feet vertical navigation clearance. This is a critical milestone towards receiving a bridge clearance permit to replace the functionally obsolete 108-year-old Interstate Bridge connecting the two states.

“This project is critical for Washington state,” Washington Governor Bob Ferguson said. “A fixed span removes the only stoplight on I-5 between Canada and Mexico, supports our economy and has broad consensus across many stakeholders. Reaching agreement between all four river users for the first time shows a clear path forward.”

A replacement fixed-span bridge would continue to provide access for 99% of river traffic, while removing the stoplight on Interstate 5 to improve safety and reliability for roadway commerce, vehicles and transit. The impacts to identified river users have now been mitigated through the agreements. There is strong regional and community support that a fixed-span bridge would best address the needs of all users.

“The IBR Program has demonstrated that a fixed-span bridge is the best solution for the largest number of users for the future transportation reliability and safety the region needs,” Oregon Governor Tina Kotek said. “I appreciate Governor Ferguson’s partnership in making sure we can get to the next milestone for the new bridge.”

A new movable span would perpetuate the same issues travelers experience with the existing movable bridge, including travel delays, reduced freight mobility and a high crash rate. Based on past estimates without accounting for inflation, construction of a movable span bridge would cost approximately half a billion dollars more (in 2022 dollars) than a fixed span and would cost $1 million more per year to operate and maintain. By comparison, these agreements totaling $140 million represent a more cost-effective solution to advance the IBR Program to construction. Payments will only be made if the Coast Guard permits a fixed-span bridge and construction begins.

River User Agreement Process

The IBR Program conducted extensive analysis and outreach to better understand the potential impacts to river users resulting from a fixed-span bridge with 116 feet of clearance. River users were identified as businesses that own or operate vessels that navigate the Columbia River, or manufacture products shipped under the Interstate Bridge. The IBR Program engaged independent experts to assess these potential impacts based on industry data and information provided directly from river users.

Comprehensive valuation processes were conducted to analyze current and projected business conditions using a thorough review of operations, vessels characteristics, site capabilities, employment data, financial statements and future revenue forecasts. It also considered potential business losses resulting from lost market opportunities and potential effects from changes to river users’ operations. An additional independent assessment was conducted, which validated that the process supporting negotiations was appropriate and adequate.

These agreements are intended to support the continued operation of these businesses at their current locations and in the region and demonstrate to the Coast Guard that the Program has addressed potential impacts.

Next steps to USCG revised decision on fixed or movable bridge

Next steps include the Coast Guard reviewing the information provided in the Program’s updated NIR. The Coast Guard will then hold a 30-day navigation comment period for river users and review those comments. At the conclusion of these steps, the states are hopeful that the Coast Guard will issue a revised Preliminary Navigation Clearance Determination for a fixed-span bridge. The Coast Guard’s decision is expected in early 2026.

Following this process, the Program’s federal lead agencies in the environmental review process – the Federal Highway Administration and Federal Transit Administration – can issue an Amended Record of Decision approving the Program to move into construction.

Hyperlinks within the release:

Updated Navigation Impact Report 
Visualizations of fixed and movable span design options
Work conducted by the IBR Program to respond to Coast Guard concerns

About the Interstate Bridge Replacement Program

The IBR Program is a bi-state effort to replace the aging Interstate Bridge with a modern, seismically resilient multimodal corridor that addresses six critical transportation challenges in this area. These challenges include safety, congestion, earthquake vulnerability, impaired freight movement, a lack of transit options, and inadequate and active transportation facilities. The Program’s mission is to improve safety for all users of the Interstate Bridge by addressing outdated roadway elements such as narrow lanes, a lack of safety shoulders and poor sight lines. Proposed investments are expected to reduce crashes, better accommodate the increase in travelers, improve emergency response, facilitate the movement of goods and services, and support more reliable travel. By relieving congestion and supporting mobility, Program investments will help drive economic growth and keep the region competitive. Program development follows a transparent and data-driven process that includes collaboration with local, state, federal and tribal partners.